July 2009 Restoration Progress
1st July 2009 to 31st July 2009
<-- Index | Showing 1-12 of 12 pictures | Index -->
The chassis on the unloading road at Toddington.
The chassis on the unloading road at Toddington.
The chassis loaded up and ready to go to Llangollen.
The chassis loaded up and ready to go to Llangollen.
Making a new lamp bracket for the tender.
Making a new lamp bracket for the tender.
Removing the tender weyshaft bracket.
Removing the tender weyshaft bracket.
Repairing the tender toolbox lids.
Repairing the tender toolbox lids.
Drilling out to fit the new 'rivet'.
Drilling out to fit the new 'rivet'.
Removing old paint from the tender. Note the remains of the BR symbol applied at Llangollen for the Steel, Steam and Stars gala, 2007.
Removing old paint from the tender. Note the remains of the BR symbol applied at Llangollen for the Steel, Steam and Stars gala, 2007.
Cutting the tender weyshaft bracket.
Cutting the tender weyshaft bracket.
The tender weyshaft parts re-fitted, showing the gap where the bracket was made too small.
The tender weyshaft parts re-fitted, showing the gap where the bracket was made too small.
Constructing a platform to allow easier and safer work on the tender.
Constructing a platform to allow easier and safer work on the tender.
The new 'rivet' fitted.
The new 'rivet' fitted.
Painting the exposed metal.